Circular 171 / 19.06.07 / House Painting Programme
Further to circular 166 posted on 27.04.07, CGM can confirm that following
our AGM on 2 June a lottery took place to determine the 20 Lodges that
would be included in the 2007 external painting programme.
CGM can confirm that only 26 of the remaining 35 unpainted Lodges qualified
for inclusion in the draw on the basis of Management Charges being paid
up to date. The Lodge numbers drawn (in order of draw) are as follows:
- 68, 75, 54, 79, 48, 80, 78, 72, 61, 77, 71, 57, 58, 69, 49, 73, 67,
83, 53 and 70.
Painting of the above Lodges will be commence after the summer letting
season provided CGM is in funds to do so and the relevant owners have
paid their management fees up to date including the second moiety.
Painting of the remaining Lodges (excluding properties where management
fees are not paid up to date) will commence in Spring 2008.
Clifden Glen Management (2005) Plc.,
Market House, Churchtown, Mallow, Co. Cork.
Click here to return to the Noticeboard
list.
|