Circular 112 / 7.12.2005 / Lodge external repainting programme / 2006.
Updated 8th March 2006
Circular 112 / amended
Completed Lodges are set in a blue font for ease of reference.
In 2005 we repainted 20 Lodges costing in excess of €50,000. This
cost is included in the management charge spread across all owners. CGM
has now issued instructions to Clifden Glen Services to repaint the following
shareholders Lodges:
Phase 1/2006
6 RC (completed)
9 CdB completed)
15 KD (completed)
18 FAA (completed)
19 RMcM (completed)
Phase 2 / 2006 (subject to prompt payment of management fees by
all owners)
23 TK (completed)
28 HK (completed)
33 L&A F (completed)
34 SD & AB (completed)
35 Reps of MC (completed)
Phases 3 / 2006 (subject to prompt payment of management fees by all
owners)
36 PS (completed)
37 M&GD (completed)
38 TT&G (completed)
39 D & O'M (completed)
41 BH (completed)
Phases 4 / 2006 (subject to prompt payment of management fees by
all owners)
42 GD (completed)
43 KL (completed)
45 GM
46 GM
47 AE
Any property whose management fee is not paid to date will be skipped
and not re-painted.
Lodge 56 is being redecorated at the special request
of the owner (who is advancing the monies to CGM). Completed in January
2006.
Each phase will be authorised based on a review of CGM cash flow which
is a function of management fee collections.
CGS will be using similar long lasting material in the redecoration to
that used in 2005.
How do we decide who to paint? We started at number 1 and see if they
are a shareholders and worked our way sequentially.
As soon as the Lodges are all repainted we will start on the Cottages
which thankfully are in good condition.
Management time: 60 minutes including dealing with CGS.
Issued by:
Clifden Glen Management (2005) Plc
Market House, Churchtown. Mallow, Co Cork
Management time: 1 hours